Plan and Control the Project Schedule

Step 35 of 57

PMP Schedule Control: Baselines, Variance, and Recovery

Introduction

Project schedule control compares the current forecast with the approved schedule and helps the team decide how to respond. A late activity matters most when it affects a milestone or the forecast finish. This lesson continues Process Task 8 of the July 2026 PMP Examination Content Outline (ECO). Process accounts for 41% of exam coverage. Start with building the schedule and calculating float if you need to refresh the scheduling calculations.

Learning objectives

  • Define the schedule baseline and explain when it can change.
  • Execute the schedule management plan, collect progress data, and update the schedule.
  • Compute SV, SPI, and interpret them; read float consumption and critical path changes.
  • Apply schedule compression (crashing, fast tracking), resource optimization, and scope-based options.
  • Analyze variation in agile projects with burndown, burnup, velocity, and cycle time.
  • Process schedule changes, forecast completion, and communicate with stakeholders.

1. The schedule baseline

The schedule baseline is the approved version of the schedule model that can be changed only through formal change control procedures. It is used as the basis for comparison with actual results. It includes the agreed start and finish dates and is one component of the performance measurement baseline, along with the scope and cost baselines.

Distinguish:

Item What it is Who can change it
Schedule model / working schedule The current, updated schedule showing progress and forecasts Project manager and team, as work progresses
Schedule baseline The approved version used for comparison Only through approved change requests
Schedule reserve Time added for identified risks, inside the baseline Used per the reserve policy, with approval as required
Management reserve of time Unidentified risk allowance, outside the baseline Requires sponsor or governance approval

A baseline should be set after the schedule is realistic, resource-loaded, and agreed with stakeholders. Rebaseline only when the applicable change authority approves a change to the baseline. Keep the history and report the current variance against the applicable approved reference.

Baselines in adaptive projects

An adaptive team may update a roadmap and release forecast as it learns. A forecast and a Sprint Goal serve different purposes from a formal baseline. When a hybrid project has approved dates, compare actuals and forecasts with those dates while the team adjusts its iteration plans.

2. Execute the schedule management plan

The schedule management plan sets the methods, tools, units of measure, thresholds, reporting formats, and procedures for updating the schedule. Execution means doing the work according to the plan and gathering performance data:

  • Percent complete, remaining duration, and actual start and finish dates (predictive).
  • Completed stories against the definition of done, burn data, and cycle time (agile).
  • Issues, impediments, risks triggered, and approved changes.

The project manager should:

  1. Collect actual dates and remaining durations as of a consistent status date. If using earned value, apply the agreed credit rules, such as 0/100 or weighted milestones.
  2. Update the working schedule and re-run the critical path.
  3. Compare to the baseline and check thresholds. For example, the project may require escalation if a milestone is forecast to slip by more than five working days or SPI falls below 0.90.
  4. Forecast completion and prepare options for variances that exceed thresholds.
  5. Communicate to stakeholders using agreed formats.

Reading float consumption

A change in float tells a story. If an activity with 10 days of float has now only 2 days, the path is becoming near-critical even though the project end date is unchanged. A project manager monitors the float of near-critical paths because small delays can shift the critical path. When two paths are within a few days of each other, risk to the end date rises.

3. Analyze schedule variance with earned value

See interpreting earned value indicators for the measures behind these two indicators.

  • Schedule variance (SV) = EV - PV. A negative value means the budgeted work performed is below the amount planned for the status date.
  • Schedule performance index (SPI) = EV / PV. A value below 1 means EV is below PV when PV is positive.

Worked example: SV and SPI

Scenario. A project has a budget at completion of 600,000. At the status date, planned value is 270,000 and the budgeted value of work performed is 225,000. Actual cost is 240,000.

Step 1: SV. 225,000 - 270,000 = -45,000 (behind schedule in value terms).

Step 2: SPI. 225,000 / 270,000 = 0.83. Earned value is about 83% of planned value at that date.

Step 3: interpret. SPI compares budgeted amounts. Update the schedule with actual progress, remaining durations, dependencies, and calendars to estimate the finish date. A 12-month plan and an SPI of 0.83 alone do not determine the duration.

Step 4: caveat. SV and SPI in cost terms can mislead: late non-critical work lowers SPI without delaying the project, while a delayed critical activity may represent small value yet delay the end date. Always check the critical path.

Step 5: act. Look for the cause. If a critical activity drives the delay, evaluate whether it can be shortened. If availability is the cause, test options in the resource-loaded forecast.

Why other readings are weaker. Deciding the project is only 15% late from the 0.83 value alone is wrong; SPI does not equal the delay in time. Ignoring the variance because the cost is near plan (CPI = 225/240 = 0.94) confuses cost with time. Rebaselining immediately hides the variance.

Earned schedule (optional concept)

Earned schedule converts earned value into time: the time at which the current EV should have been earned in the plan. If EV of 225,000 equals the planned value at month 4.2, and actual time is 5.4 months, the schedule variance in time is 4.2 - 5.4 = -1.2 months. SPI(t) = 4.2 / 5.4 = 0.78. This expresses variance in time units. Check the baseline curve and status date, and use the network and current conditions to assess the actual finish.

4. Schedule compression and recovery options

When the schedule is late or the end date is moved earlier, compression shortens the schedule without reducing scope.

Technique What it does Effect on cost Effect on risk Applies when
Crashing Add resources to critical path activities Cost rises Moderate (coordination, learning curve) Activities are resource-sensitive and a cost trade-off is acceptable
Fast tracking Overlap work that was planned in sequence May add coordination or rework cost Rework risk may rise Overlap is feasible under the dependencies and constraints

To shorten the finish, target activities or links that drive it. Recalculate after every change. If two paths drive completion, shorten both or a shared activity. Compare feasible combinations by cost, time saved, and risk.

Worked example: crashing with cost slope

Scenario. The critical path A-B-D-F is 17 days and a client wants delivery in 15 days. Crash data:

Activity Normal duration Crash duration Extra cost for full crash
A 4 3 1,000
B 6 4 3,000
D 5 4 2,500
F 2 2 not crashable

The other path A-C-E-F is 16 days and also contains A. Assume the cost of crashing B is linear and the work can be shortened in whole-day steps.

Step 1: cost slope per day. A: 1,000 per day. B: 3,000 / 2 = 1,500 per day. D: 2,500 per day.

Step 2: crash the cheapest first. A is on both paths, so crashing it by 1 day (cost 1,000) shortens A-B-D-F to 16 days and A-C-E-F to 15 days.

Step 3: crash the next cheapest on the remaining critical path. A-B-D-F is still the longest (16 days). B costs 1,500 per day, less than D at 2,500. Crashing B by 1 day gives A-B-D-F = 3 + 5 + 5 + 2 = 15 days. A-C-E-F = 3 + 3 + 7 + 2 = 15 days. Both paths are now 15 days and the target is met.

Step 4: total cost. 1,000 (A by 1) + 1,500 (B by 1) = 2,500.

Step 5: consider risks. Crashing A and B adds coordination effort and may reduce quality; the project manager checks resource availability and agrees the extra cost through change control.

Why other choices are weaker. Crashing D costs 2,500 for one day, more than B. Crashing F is impossible. Crashing a non-critical activity (such as C) adds cost without shortening the project.

Other recovery options

  • Resource optimization: reassign skilled people to critical tasks; resolve overallocations.
  • Reduce scope or defer lower-value items (for example, moving stories out of the release), agreed with the sponsor and product owner.
  • Improve productivity: remove impediments, add automation, improve the team environment.
  • Reduce rework: a good quality plan prevents schedule loss.
  • Change dependencies: negotiate leads, parallel work, or earlier supplier delivery.
  • Adjust the end date: if compression is too costly or risky, present a revised date to the sponsor for approval.

Do not cut quality or testing silently to recover time. That moves the problem to later and increases cost of nonconformance.

5. Analyze variation in agile projects

Predictive metrics like SV rely on a baseline. Agile teams use direct measures of progress and flow.

Tool What it shows How to read it
Burndown chart Remaining work against time Above a reference line means more work remains than that reference assumed
Burnup chart Completed work and total scope over time Shows scope growth separately from progress
Velocity Points completed per iteration Used for forecasting; stable velocity suggests predictability
Cumulative flow diagram Work items in each state over time A widening band indicates accumulation. Investigate blocked work, arrivals, and departures.
Cycle time and lead time Time from work start to finish, or from request to finish, using defined endpoints A rising trend prompts investigation of item size, queues, and blockers
Throughput Items completed per period Used in flow-based forecasting

Burnup versus burndown

A burndown chart can hide scope changes: if the line is flat, is the team slow or was new work added? A burnup chart shows the total-scope line separately, so you can see that the team completed 12 points while scope grew by 10. Use burnup for stakeholders interested in scope changes.

Worked example: reading a burnup chart

Scenario. After 5 two-week iterations, a team has completed 150 points. Total scope was 300 points at the start and is now 340 points, because 40 points of new stories were approved. The release is planned for 10 iterations.

Step 1: velocity. 150 / 5 = 30 points per iteration.

Step 2: remaining work. 340 - 150 = 190 points.

Step 3: forecast. 190 / 30 = 6.3, so about 7 more iterations, 12 in total versus 10 planned: about 2 iterations late.

Step 4: options for the product owner.

  • Move 60 points of eligible lower-priority work out of the release. At the same rate, 130 points need five whole iterations, for ten in total. Check the dependencies and commitments before choosing items.
  • Extend the release by two iterations.
  • Compare a capacity change against onboarding time and the team’s ability to work in parallel.

Step 5: decide with the product owner and sponsor. The project manager shows the burnup, the forecast assumptions and the options. The Product Owner orders the backlog within their authority, and any change to the release commitment goes to its approver.

Why other choices are weaker. Telling the team to work overtime treats a symptom and endangers sustainable pace. Hiding the scope growth makes the team look unproductive. Rebaselining a fixed release date without a scope trade-off ignores the sponsor's constraint.

Impediments

Schedule variance in agile often traces to impediments: blocked environments, waiting for decisions, unclear acceptance criteria, or team changes. The project manager or servant leader removes or escalates them quickly. Limiting work in progress and visualizing blocked items on the board make delays visible early.

6. Handling schedule changes

When analysis shows the schedule needs to change:

  1. Assess the cause and impact (critical path, cost, risk, quality, scope, resources).
  2. Identify options such as crashing, fast tracking, reducing scope, or accepting a revised date.
  3. Raise a change request with the analysis, for approval by the change control board or authorized decision maker, per the plan.
  4. After approval, implement, update the schedule, and rebaseline if the approved change affects the baseline.
  5. Communicate the decision and update the affected records, such as the risk register, issue log, and forecasts.

Distinguish a schedule issue (already happened) from a schedule risk (may happen). Delays caused by a supplier that has already failed to deliver are an issue; the possibility that a supplier may be late is a risk to respond to in advance with a plan.

Schedule reserve use

Use schedule reserves for identified risks as planned: if a risk event occurs and the response consumes 3 days of the schedule reserve, record it, update the forecast, and report the remaining reserve. If the reserve is nearly exhausted and risks remain, escalate early rather than waiting for the baseline to be missed.

7. Reporting schedule status

Schedule reports should answer: where are we, why, what is the forecast, what are we doing, and what do we need from the stakeholders. Tailor the format:

Audience What they need Format
Sponsor, steering committee Forecast finish date, milestone status, decisions needed One-page summary, RAG status, milestone chart
Team Tasks, dependencies, impediments Task board, Gantt, daily stand-up
Customer / product owner Release forecast, scope trade-offs Burnup chart, roadmap
PMO / governance Variance against thresholds, trend Dashboard with SPI, float, and milestone trend

Use trends rather than single points. Be transparent: reporting bad news early gives the sponsor time to act. Include a forecast and the recommended response, not only the problem.

8. Common pitfalls and exam tips

  • Pitfall: changing the baseline without approval. Baseline changes need change control.
  • Pitfall: compressing non-critical work. It does not shorten the project.
  • Pitfall: choosing crashing when the issue is poor requirements. Fix the cause, not only the symptom.
  • Pitfall: relying on SPI alone. Check the critical path.
  • Pitfall: hiding scope growth. Show it with burnup charts.
  • Pitfall: asking for overtime as the first move. It is unsustainable and may reduce quality.

Exam tip: Crashing adds cost, fast tracking adds risk. Assess the cost and rework risk of overlapping activities. Confirm that mandatory sequencing and quality checks can still be met.

Exam tip: If the project manager discovers a delay, the first step is usually to analyze the cause and impact before taking action, unless the scenario says action is urgent.

Exam tip: Use recent delivery data when conditions are comparable. Involve the Product Owner in backlog decisions and preserve any separate approved milestones.

Exam tip: Whenever a change to the baseline is proposed, the answer involves a change request and the approval route.

9. Mini case study: the slipping data migration

Context. A project to migrate a customer database has a baseline end date of 30 June. At the end of March, the status shows PV = 400,000, EV = 320,000, AC = 330,000. The critical path runs through "data cleansing", planned for 20 days and now estimated at 32 days because the source data quality is worse than expected. A parallel activity, "build reports", has 10 days of float. The sponsor insists on 30 June. The team has two free data engineers from another project, and there are discretionary dependencies between cleansing and mapping design.

Question. What should the project manager do?

Solution (commented).

  1. Compute the metrics. SV = 320,000 - 400,000 = -80,000. SPI = 320 / 400 = 0.80. CPI = 320 / 330 = 0.97. The main problem is schedule, not cost.
  2. Confirm with the critical path. The estimate for cleansing rose by 12 working days. If it remains on the driving path and downstream assumptions are unchanged, the finish slips by 12 working days. Check that result in the updated network.
  3. Find the root cause. Poor data quality was an assumption that proved false. Update the risk register and look for similar assumptions.
  4. Generate options. (a) Crash: add the two engineers to cleansing; if this cuts 8 days, the delay falls to 4 days, at a cost of extra effort. (b) Fast track: begin mapping design on cleansed subsets while cleansing continues, accepting rework risk. (c) Defer low-value report features to a later release, with the sponsor's agreement. (d) Negotiate the date.
  5. Combine and evaluate. Model crashing and fast tracking together. Their benefits can overlap or shift the driving path, so calculate the combined finish and estimate the rework exposure. Do not compress "build reports" because it is non-critical.
  6. Raise a change request with analysis and a recommended option; obtain approval; update the schedule and report.
  7. Communicate with the sponsor immediately rather than waiting for the next report, showing the forecast date with and without action.
  8. Do not rebaseline to 12 days later without an approved change, and do not tell the team to skip data validation to save time.

Key terms

  • Schedule baseline: approved schedule used for comparison; changed only via change control.
  • Schedule variance (SV) and SPI: EV - PV, and EV / PV.
  • Crashing: adding resources to shorten the critical path, at extra cost.
  • Fast tracking: overlapping activities that were sequential, with rework risk.
  • Burndown / burnup chart: remaining work / completed work and scope over time.
  • Velocity: points completed per iteration.
  • Cycle time: time to complete one item once started.
  • Cumulative flow diagram: work items per state over time, showing bottlenecks.
  • Schedule reserve: time added to the baseline for identified risks.
  • Earned schedule: converts earned value into time.

Summary checklist

  • I know what the schedule baseline is and how it can change.
  • I can compute SV and SPI and recognize their limits.
  • I can pick crashing or fast tracking and explain the trade-offs.
  • I can choose the cheapest crash path using cost slope.
  • I can read a burnup chart and forecast from velocity.
  • I process schedule changes through change control.
  • I distinguish a schedule issue from a schedule risk.
  • I tailor schedule reports to the audience and include recommended actions.