Plan and Monitor Project Finances

Step 30 of 57

PMP Financial Performance: Earned Value and Cost Forecasting

Introduction

Earned value management compares the budgeted work performed with the plan and its actual cost. Spending less than planned can still signal trouble if even less work has been completed. This lesson continues Process Task 6 in the July 2026 PMP Examination Content Outline (ECO). Process accounts for 41% of exam coverage. After building the cost baseline and reserves, you will calculate indicators, choose a cost forecast, and act on variances within project governance.

Learning objectives

  • Define PV, EV, and AC, and compute CV, SV, CPI, and SPI.
  • Forecast EAC with the four standard formulas and choose the right one for the situation.
  • Compute ETC, VAC, and TCPI, and interpret them.
  • Interpret an S-curve and a variance report, and decide on corrective action.
  • Follow governance when variances exceed thresholds, including reserve use and baseline change.
  • Anticipate future financial challenges such as inflation, currency, supplier price changes, and funding cuts.
  • Monitor money on agile and hybrid projects with burn charts and value-based indicators.

1. Earned value management in one picture

Earned value management (EVM) uses linked measures to compare scope performed, schedule progress, and cost against a common plan. Three values at a status date:

Term Name Meaning
PV Planned value The authorized budget for the work scheduled to be done by the status date
EV Earned value The authorized budget for the work actually completed by the status date
AC Actual cost The cost incurred for the work performed by the status date, including applicable accruals

And the budget at completion (BAC): the total planned value of the project (the cost baseline).

Variances and indices

Metric Formula Positive or above 1 means Negative or below 1 means
Cost variance (CV) EV - AC Under budget Over budget
Schedule variance (SV) EV - PV Ahead of schedule Behind schedule
Cost performance index (CPI) EV / AC Under budget (value per euro spent) Over budget
Schedule performance index (SPI) EV / PV Ahead of schedule Behind schedule

Remember: EV is always the first term. CPI of 0.90 means that for every euro spent only 90 cents of planned value has been earned.

Measuring earned value

How EV is measured must be defined in the cost management plan before work starts: 0/100 (credit only when done, for short tasks), 50/50 (half when started, half when done), weighted milestones, equivalent units, or percent complete (subjective and less reliable). Early reports claiming 90% complete for weeks, the "90% syndrome", are a warning that percent complete is being guessed.

Worked example: a status report

Statement. A project has a BAC of EUR 600,000. At the end of month 6, the budgeted value of scheduled work is 50% of BAC. The budgeted value of work performed is 40% of BAC, and the team has incurred EUR 270,000. Compute PV, EV, AC, CV, SV, CPI, and SPI, and interpret them.

Reasoning.

  1. PV = 50% x 600,000 = 300,000.
  2. EV = 40% x 600,000 = 240,000.
  3. AC = 270,000.
  4. CV = EV - AC = 240,000 - 270,000 = -30,000 (over budget).
  5. SV = EV - PV = 240,000 - 300,000 = -60,000 (behind schedule).
  6. CPI = 240,000 / 270,000 = 0.89.
  7. SPI = 240,000 / 300,000 = 0.80.

Interpretation. The project is both over budget and behind schedule. For each euro spent, 89 cents of value has been earned. The team has earned 80% of the budgeted value scheduled by the status date. SV in money terms (-60,000) is not a time; to see time impact, look at the critical path or use earned schedule.

Why other answers are wrong. Using PV - EV for the schedule variance reverses the sign. Using AC / EV for the cost index gives the inverse, which is a different measure. Calling the project "on track because spend (270,000) is below PV (300,000)" ignores that less work was done than planned.

2. Forecasting: EAC, ETC, VAC

Forecasting estimates the cost at completion (EAC) and the remaining cost (ETC).

Situation EAC formula Explanation
Original estimate was flawed and a new estimate is needed EAC = AC + bottom-up ETC Re-estimate the remaining work
Current variance is atypical and will not repeat EAC = AC + (BAC - EV) Remaining work at planned rate
Current cost performance continues EAC = BAC / CPI Assumes remaining work has the same cost efficiency as work so far
Both cost and schedule performance influence the cost EAC = AC + [(BAC - EV) / (CPI x SPI)] A forecast model for scenarios where both indices are expected to affect remaining cost

Other forecasts:

  • ETC (estimate to complete) = EAC - AC (or the bottom-up ETC).
  • VAC (variance at completion) = BAC - EAC. Negative means a forecast overrun.
  • TCPI (to-complete performance index) = (BAC - EV) / (BAC - AC) when aiming at the BAC; = (BAC - EV) / (EAC - AC) when aiming at a new EAC.

The TCPI is the cost efficiency the team must achieve for the remaining work to meet the target. Compare TCPI with past CPI and the characteristics of the remaining work. A large gap calls for evidence of an improvement. If the remaining funds in the denominator are zero or negative while work remains, the target has no positive funding left.

Worked example: forecasting with the same project

Using BAC = 600,000, EV = 240,000, AC = 270,000, CPI = 0.889, SPI = 0.80.

Statement. Compare three index-based forecasts, then calculate ETC, VAC, and TCPI to BAC. A bottom-up forecast would need a separate estimate of remaining work. Which forecast should the project manager use if the overspend came from a one-off supplier error that has been fixed?

Reasoning.

  1. Remaining work at planned cost: EAC = AC + (BAC - EV) = 270,000 + (600,000 - 240,000) = 270,000 + 360,000 = EUR 630,000.
  2. Typical variance (CPI continues): EAC = BAC / CPI = 600,000 × 270 / 240 = EUR 675,000.
  3. CPI x SPI: CPI x SPI = 0.8889 x 0.80 = 0.7111; EAC = 270,000 + 360,000 / 0.7111 = 270,000 + 506,250 = EUR 776,250.
  4. For the one-off error, if remaining work can be delivered at the planned rate, use the atypical formula: EAC = 630,000.
  5. ETC = EAC - AC = 630,000 - 270,000 = 360,000.
  6. VAC = BAC - EAC = 600,000 - 630,000 = -30,000 (the original overrun is carried but no more is expected).
  7. TCPI to BAC = (600,000 - 240,000) / (600,000 - 270,000) = 360,000 / 330,000 = 1.09. The team would need 1.09 value per euro for the rest to finish on budget, which is above the 0.89 achieved so far, so finishing at BAC is unlikely.

Solution. EAC 630,000, ETC 360,000, VAC -30,000, TCPI to BAC 1.09.

Why other answers are weaker. BAC / CPI assumes the same inefficiency continues, which contradicts the information about a one-off cause. The CPI x SPI formula applies when the schedule pressure will add cost, such as overtime or crashing, which the scenario does not say. Reporting EAC = BAC ignores real information.

Choosing the formula from the wording

  • "The variance is a one-time event" or "will not recur": AC + (BAC - EV).
  • "Remaining work will continue at the observed cost efficiency": BAC / CPI. When the assumption is unclear, check the remaining cost drivers.
  • "The original estimate is no longer valid" or "new estimate": AC + new ETC.
  • "Remaining costs will reflect both cost and schedule performance": consider the CPI × SPI formula and check it against the recovery plan.

3. Reading a project's financial story

Numbers alone do not give the answer. Interpret them with the schedule and the risk picture.

CPI SPI Typical reading Typical response
> 1 > 1 Under budget and ahead Check estimates; bank gains cautiously; verify quality
> 1 < 1 Efficient but slow Check resource availability; fast tracking or more capacity if value justifies
< 1 > 1 Fast but expensive Overtime or premium resources; review cost control and benefits
< 1 < 1 Over budget and late Root cause analysis; scope, resource, and risk review; escalate with options

The S-curve

Plot PV, EV, and AC against time. When EV is below PV, less budgeted work has been performed than planned. When AC is above EV, the work performed cost more than its budgeted value. Check the direction of each gap, the activity network, and the timing of recorded costs before attributing a trend. The gap between EV and AC at a point in time is the cost variance, and the gap between EV and PV the schedule variance.

Trend analysis

A single month can mislead. Track CPI and SPI over several periods. A CPI that stays near 0.90 is a stable pattern; a CPI that falls from 1.0 to 0.80 over three months is a deteriorating trend and needs action even if the cumulative figure still looks acceptable. Review both period and cumulative indices. The cumulative figure can mask a recent change in rates or performance.

Reserve analysis

Compare the remaining contingency to the remaining risk. If EUR 40,000 of contingency remains but the open risks have an EMV of EUR 65,000, the reserve is EUR 25,000 below the estimated exposure on that basis. Check the risk distribution and funding policy, then discuss response options with the sponsor. If risks have passed, release the unused contingency according to the organization's rule, not by spending it on extras.

4. Acting on variances within governance

Variances within the agreed threshold are managed by the project manager within the plan. Variances beyond the threshold need a formal response.

  1. Verify the data. Check applicable accruals for work performed, the measurement of EV, and the common status date. Track open commitments separately in the forecast.
  2. Find the root cause. Was it an estimating error, scope growth, rate increases, rework, resource inefficiency, a supplier issue, or an external factor? Use a cause-and-effect diagram or five whys.
  3. Evaluate options. Reduce or reprioritize scope, improve productivity, change suppliers or contract terms, use contingency, fast track or crash if schedule drives cost, or request additional funding.
  4. Assess the impact on schedule, quality, risk, benefits, and stakeholders.
  5. Decide and request approval. Use contingency within your authority. Use management reserve or change the baseline only through change control with the sponsor or the change control board.
  6. Communicate. Tell the sponsor and stakeholders early, with facts, the forecast, and the proposed action. No surprises.
  7. Update the forecast, the risk register, the lessons learned, and, if approved, the baseline.

Do not rebaseline merely to make the variances disappear. A baseline changes only when an approved change alters the scope, schedule, or budget. Hiding a variance by shifting costs into another account is an ethical and compliance problem.

Worked example: choosing a response

Statement. A software project has BAC EUR 900,000, EV 300,000, AC 360,000, and PV 330,000. The sponsor requires escalation if CPI falls below 0.90 or rises above 1.10. Assume the observed aggregate cost efficiency will continue. Calculate CPI and SPI, state whether escalation is needed, and propose a response, given that the overrun comes from underestimated testing effort that will continue.

Reasoning.

  1. CPI = 300,000 / 360,000 = 0.83; SPI = 300,000 / 330,000 = 0.91.
  2. CPI ≈ 0.83 is below 0.90, the lower end of the agreed band. Escalate to the sponsor.
  3. Under the stated cost-efficiency assumption, EAC = BAC / CPI = 900,000 × 360,000 / 300,000 = EUR 1,080,000 and VAC = −EUR 180,000.
  4. TCPI to BAC = (900,000 - 300,000) / (900,000 - 360,000) = 600,000 / 540,000 = 1.11, which requires substantially greater efficiency than the CPI of 0.83 achieved so far.
  5. Options: (a) reduce scope with the product owner by moving lower-value features out; (b) add test automation to improve productivity, which has an up-front cost but lowers the cost of repeated testing; (c) request additional funds or management reserve through change control; (d) combine (a) and (b).
  6. Present to the sponsor: forecast 1,080,000, options with costs and effects, a recommendation, and a decision date.

Solution. Escalate with a forecast of EUR 1,080,000 and a recommended combination of scope reprioritization and test automation, with a change request for any extra funding.

Why other responses are weaker. Quietly using management reserve breaks governance. Cutting testing to save cost damages quality and creates a larger future cost. Waiting for another reporting period lets the trend worsen.

5. Anticipating future financial challenges

A project manager looks forward as well as back. Typical factors:

  • Inflation and price escalation on long projects or procurement; use economic price adjustment clauses or add allowance.
  • Currency exchange when suppliers or customers use other currencies; ask finance or treasury to assess exchange-rate exposure and the responses allowed by policy.
  • Supplier insolvency or price increases; monitor supplier financial health, keep alternatives.
  • Funding cuts or reprioritization by the organization; keep the business case current and communicate value delivered.
  • Resource rate changes (salary increases, contractor rates).
  • Regulatory changes that add compliance cost.
  • Technology costs, including cloud usage that grows with consumption; track usage-based costs against forecast and set alerts.
  • Sustainability and energy costs, where energy price or carbon rules affect operating costs.
  • AI-assisted analysis can support forecasting with historical data and pattern detection; the project manager still checks assumptions and keeps accountability for the decision.

Scenario planning helps: define best, expected, and worst cases for the forecast, and the triggers that would move the project from one to another.

6. Agile and hybrid financial monitoring

To use EVM in adaptive delivery, link completed work to an approved, time-phased budget and reconcile actual costs for the same work. Points alone do not establish earned value. See integrating forecasts into the project management plan for linking forecasts with the rest of the plan. Depending on reporting requirements, other indicators can help:

  • Budget burn-down: remaining budget over time, alongside a separate measure of remaining work.
  • Release burn-up: completed scope (story points) against total scope, compared to money spent.
  • Cost per delivered story point or per feature, trended over time.
  • Forecast to complete: remaining points divided by velocity gives the number of iterations left; multiplied by the cost per iteration it gives the forecast cost.
  • Value delivered earlier: the percentage of the high-value backlog delivered at a given spend.

Example: agile forecast

A team costs EUR 60,000 per iteration. The release backlog is 400 points, 160 are done after 4 iterations, and the average velocity is 40 points. Remaining points: 240. Iterations left: 240 / 40 = 6. Forecast remaining cost: 6 x 60,000 = 360,000. Total forecast: 4 x 60,000 + 360,000 = 600,000. If the approved budget is 550,000, the team has EUR 310,000 left after four iterations. At full-iteration cost that funds five more iterations, or about 200 points at the same delivery rate. Compare deferring about 40 points of optional work, negotiating capacity changes, or seeking approval for more funding. Check dependencies and benefit impacts with the Product Owner.

In hybrid projects, report predictive components with EVM and agile components with burn charts, then combine at the level of total committed spend and forecast.

7. Common pitfalls and exam tips

Pitfalls

  • Mixing up the formulas: CV = EV - AC (not AC - EV).
  • Using BAC / CPI when the scenario says the cause was one-off.
  • Reading SV in money as a time delay.
  • Ignoring commitments and accruals, so AC looks better than reality.
  • Rebaselining to remove variance without an approved change.
  • Using management reserve without approval.
  • Reporting only the cumulative figures and missing the trend.
  • Waiting for a formal report to tell the sponsor about a known overrun.

Exam tips

  • EV comes first in CV, SV, CPI, and SPI.
  • Choose an EAC formula from the stated assumptions. Use BAC / CPI for continuing cost efficiency and AC + BAC − EV when remaining work is expected to cost its planned amount.
  • VAC = BAC - EAC; ETC = EAC - AC; TCPI > 1 means harder to achieve.
  • When an indicator breaches tolerance, analyse the cause and escalate under the agreed rules. Submit any proposed baseline change for approval.
  • Check the delegated authority and process for each reserve drawdown.
  • The best answer is rarely "reduce quality to save money" or "hide the figures".
  • In agile, forecast with velocity and cost per iteration, and cut the lowest-value scope before extending the budget.

8. Mini case study

Situation. A hospital IT modernization has BAC EUR 1,500,000. At month 8, PV is 1,000,000, EV is 850,000, and AC is 1,020,000. Remaining contingency is EUR 60,000, and open risks have an EMV of EUR 110,000. The sponsor's rule: any CPI below 0.90 triggers a formal review. The overrun is mostly caused by licence prices that rose 15% and will apply for the rest of the project. A funding review is due in six weeks.

Questions. Calculate the indicators, choose a forecast, and recommend actions.

Commented solution.

  1. CV = 850,000 - 1,020,000 = -170,000. SV = 850,000 - 1,000,000 = -150,000.
  2. CPI = 850,000 / 1,020,000 = 0.833; SPI = 850,000 / 1,000,000 = 0.85.
  3. CPI below 0.90 means a formal review is triggered. The sponsor must be informed, with a forecast.
  4. For a scenario in which the current aggregate cost efficiency continues, EAC = BAC / CPI = 1,500,000 / 0.8333 = EUR 1,800,000. VAC = −EUR 300,000 and ETC = EUR 780,000. Check this scenario against a bottom-up forecast using updated licence quotes and the costs of the other remaining work.
  5. TCPI to BAC = (1,500,000 - 850,000) / (1,500,000 - 1,020,000) = 650,000 / 480,000 = 1.35, so the BAC is not achievable at the current performance.
  6. Reserve analysis: contingency 60,000 versus open risk EMV 110,000 shows a EUR 50,000 difference relative to EMV. Check whether the forecast already includes the same risks and confirm what reserve is required under policy.
  7. Actions: (a) hold a root cause review with procurement on the licence contract and look for volume discounts or alternative licensing; (b) assess scope options with the product owner (defer two low-value modules); (c) prepare a change request for additional funding with the options and their effect on the schedule and benefits, ready before the funding review in six weeks; (d) update the risk register and the forecast monthly; (e) inform stakeholders now rather than at the funding review.
  8. What not to do: do not apply the atypical formula to appear closer to the budget; do not use management reserve without approval; do not cut testing to recover cost.

Key terms

  • PV, EV, AC, BAC: planned value, earned value, actual cost, budget at completion.
  • CV, SV: cost and schedule variance (EV - AC, EV - PV).
  • CPI, SPI: cost and schedule performance indices (EV / AC, EV / PV).
  • EAC, ETC, VAC: estimate at completion, estimate to complete, variance at completion.
  • TCPI: efficiency needed on remaining work to reach a target.
  • Cost threshold: variance limit that triggers action or escalation.
  • S-curve: cumulative PV, EV, and AC over time.
  • Reserve analysis: comparing remaining reserves with remaining risk.
  • Burn-up / burn-down: agile charts of completed work or remaining budget.

Summary checklist

  • I can compute PV, EV, AC, CV, SV, CPI, and SPI and interpret them.
  • I can choose and compute EAC, ETC, VAC, and TCPI for a scenario.
  • I can read the CPI/SPI combinations and S-curves, including trends.
  • I follow governance for variances, reserves, and baseline changes.
  • I communicate financial problems early with options.
  • I anticipate inflation, currency, supplier, and funding risks.
  • I can forecast and monitor agile budgets with velocity and burn charts.